better throughput scheduling with steady state cost model, now limited to spatial
This commit is contained in:
@@ -17,7 +17,7 @@ Boolean switches default to off unless stated otherwise.
|
||||
| `--pim-only-codegen` | Run the codegen tail on bufferized Pim IR. |
|
||||
| `--pim-emit-json` | Also emit per-core JSON instructions. |
|
||||
| `--pim-dump-ir` | Write diagnostic IR snapshots with elided large constants; default: off. |
|
||||
| `--pim-periodic-diagnostics` | Write the optional pre-codegen recurrence report; default: off. |
|
||||
| `--pim-periodic-diagnostics` | Write optional recurrence and Spatial execution-work reports; default: off. |
|
||||
| `--pim-export-spatial-dataflow=none\|spatial1\|spatial2\|spatial3\|spatial4\|all` | Export graph, trivially merged, scheduled, and realized CSV snapshots under `reports/`; default: `none`. |
|
||||
| `--pim-conv-lowering=STRATEGY` | `auto` (default), `legacy`, `depthwise`, `packed-im2col`, `streamed-patch`, `streamed-packed`, `output-channel-tiled`, `input-k-tiled`, or `tiled-2d`. |
|
||||
| `--pim-conv-im2col-max-elements=N` | Global im2col limit before streaming; default: 1048576. |
|
||||
|
||||
@@ -72,6 +72,59 @@ byte-sized elements. Blueprint assembly charges per fragment. A full fragment
|
||||
receive directly into assembly storage omits duplicate endpoint-memory edge
|
||||
cost; later copy elimination can leave this estimate conservative.
|
||||
|
||||
`CopyAccessPlan` shares ordered contiguous-run geometry between projection
|
||||
costing and PIM copy normalization. Its inputs are a logical copy shape and
|
||||
proven source and destination strides, in elements. The immutable result keeps
|
||||
outer dimensions, run count, run length, and relative offsets compact. Building
|
||||
the plan takes linear time and space in rank, independent of loop trip counts.
|
||||
It creates no IR and does not prove aliasing, storage ownership, or copy legality.
|
||||
PIM bufferization still owns those decisions and the mapping to byte accesses.
|
||||
The plan alone does not describe a complete scheduled memory-request stream.
|
||||
Construction rejects an unrepresentable maximum relative element offset,
|
||||
including the last element of each run. Callers still check byte scaling and
|
||||
base-address addition.
|
||||
Projection costing uses checked row-major strides. Unsupported flattened
|
||||
offsets or strides produce at most one warning per graph cost query. The query
|
||||
uses one separately rounded request per element as a conservative service bound.
|
||||
It does not reject otherwise valid Spatial IR. Target lowering retains its own
|
||||
address and layout legality checks. Unsupported estimates and malformed IR are
|
||||
different conditions.
|
||||
|
||||
The PIM adapter's `planComputeInputMaterialization` reads scheduled Spatial
|
||||
regions without changing them. It returns `Unused`, `ForwardConstant`,
|
||||
`ForwardFunctionInput`, or `CopyAtEntry`. Function-input normalization forwards
|
||||
host inputs into compute bodies before entry-copy materialization.
|
||||
Single-core lowering forwards used arithmetic constants. Batch lowering copies
|
||||
remaining inputs at body entry, including constants. Lowering and costing
|
||||
consume the same decisions. The query has constant time and space per
|
||||
input and does not expand lanes or loops. Abstract target work extraction uses
|
||||
the same query. Subsequent canonicalization can remove uses.
|
||||
`getReusableOutputTensor` shares read-only destination selection with vector
|
||||
lowering. It identifies a tensor operand or requires fresh storage. It does not
|
||||
prove a physical alias, assign an address, or replace one-shot bufferization.
|
||||
The result is valid only for the current SSA graph. Changes to uses, operation
|
||||
order, loop yields, or operands require recomputation. Lowering consumes this
|
||||
decision immediately; it does not cache values across rewrites. Current PIM
|
||||
bufferization consumes the explicit destination ties introduced by target
|
||||
lowering. Output-copy forwarding also consumes the resulting allocation,
|
||||
subview, copy, and dominance facts. An early destination choice alone cannot
|
||||
describe those physical aliases or the final storage lifetimes.
|
||||
Logical storage identity and physical address equality are different facts.
|
||||
Local-memory planning can assign the same address to distinct allocations whose
|
||||
lifetimes do not overlap. Scalar register setup therefore needs placement and
|
||||
instruction-order information in addition to logical alias relationships.
|
||||
Abstract cost estimates need not reconstruct these addresses.
|
||||
|
||||
This input plan does not count physical constant loads. A forwarded host
|
||||
constant can need a new local buffer at each use. Bufferization, host folding,
|
||||
alias analysis, and memory normalization determine the resulting requests.
|
||||
`isZeroBitPatternSplat` shares constant-content classification between graph
|
||||
accounting and code generation. PIM replaces eligible positive-zero and integer-zero
|
||||
loads with local fills. Negative floating zero retains its distinct bit pattern.
|
||||
Constant content is candidate-independent; input placement and buffer reuse
|
||||
depend on the realized candidate. Production uses these shared decisions when
|
||||
extracting Spatial execution events for the queue estimate.
|
||||
|
||||
Execution transpose costs share `getTransposeRun` with lowering: round memory
|
||||
reads/writes per run and add vector execution when source stride is not one.
|
||||
The [Pimsim vector unit](../../backend-simulators/pim/pimsim-nn/src/core/component/VectorUnit.cpp)
|
||||
@@ -118,3 +171,89 @@ scheduling overview. Cached PEFT center distances avoid a topology scan per task
|
||||
projection and priority analyses share/cache work rather than revisiting every
|
||||
template body per chunk. Ready-transfer signature searches remain another
|
||||
potential compile-time hotspot.
|
||||
|
||||
### Spatial execution costs
|
||||
|
||||
`SchedulingTarget::estimateRealizedScheduleCost` is a read-only query on realized Spatial IR.
|
||||
The PIM adapter extracts compact ordered execution events without constructing PIM operations.
|
||||
It uses physical core assignments, communication, input-materialization decisions, and shared copy geometry.
|
||||
No physical buffer addresses are required.
|
||||
The shared engine models controller arbitration, source FIFOs, synchronization, and repeated generations.
|
||||
Both arbitration policies are sensitivity checks, not guaranteed bounds.
|
||||
The engine returns typed intervals and recurrence evidence before diagnostic serialization.
|
||||
The target adapter adds static lowering support. Spatial owns the selection policy margin.
|
||||
JSON fields are report output and do not control availability or eligibility.
|
||||
Typed evaluation completes before reporting. Serialization never runs queue analysis.
|
||||
Only optional diagnostics construct fingerprints, traces, and per-core resource reports.
|
||||
|
||||
Normal compilation extracts costs for multiple candidates and lowers only the selected schedule.
|
||||
A single candidate bypasses the cost query entirely.
|
||||
Candidate summaries distinguish available timing, static lowering support, and proved modeled recurrence.
|
||||
Unknown support remains explicit. All candidates must satisfy these checks before comparison.
|
||||
`Unsupported` identifies a known static violation, including invalid or repeated physical-core assignments.
|
||||
`Unknown` identifies missing evidence or an unmodeled form, rather than a proven backend rejection.
|
||||
`Supported` covers checked static forms and does not prove final allocation success.
|
||||
A finite interval alone does not establish eligibility.
|
||||
|
||||
Preflight does not repeat bufferization or allocation.
|
||||
The backend owns final legality and signed 32-bit local-memory address validation.
|
||||
Resource failures marked by that owner permit an explicit retry from the original checkpoint.
|
||||
Unclassified failures stop compilation. Every attempted schedule and cause appears in the selection report.
|
||||
|
||||
### Complete-state recurrence
|
||||
|
||||
Queue analysis checks translated states at one fixed core's body entry.
|
||||
Snapshots contain completion counts relative to core entry, ready-input counts, and busy state for every event.
|
||||
Run-length encoding keeps these records compact.
|
||||
Snapshots also contain pending events in arbitration order, remaining FIFO tokens, controller availability, and the tie policy.
|
||||
One pending firing per event makes node IDs sufficient to resolve simultaneous-event ties.
|
||||
The graph and target parameters remain fixed within each query.
|
||||
Time offsets use checked unsigned differences.
|
||||
Equal states require equal positive generation progress on every core.
|
||||
This proves recurrence for the deterministic abstract model, not physical execution-time accuracy.
|
||||
Reporting counters and analysis budgets are not hardware state.
|
||||
|
||||
Token initialization distances and graph edges remain immutable within a query.
|
||||
Consumption clears a drained queue and resets its head immediately.
|
||||
Drained and never-populated queues therefore have the same readiness state.
|
||||
Consumed prefixes, capacities, and compaction indices cannot affect future timing or FIFO contents.
|
||||
An idle controller's past completion cannot delay future arrivals.
|
||||
These normalizations require causal, monotonic transitions, which the proof checks.
|
||||
|
||||
Proof construction uses at most 256 generations and 16 MiB of snapshot storage.
|
||||
Each checkpoint scans events, dependencies, and remaining tokens, then orders a copy of the pending frontier.
|
||||
Exact comparisons use bounded history; hashes only filter comparisons.
|
||||
Unproved recurrence remains explicit and cannot guide multi-candidate selection.
|
||||
When recurrence is proved, its interval is authoritative for that arbitration policy and its report.
|
||||
Proof-mode reports retain interval-window results under `legacy_interval_window`.
|
||||
Normal costing stops once recurrence is proved. Detailed diagnostics can continue to collect interval-window evidence.
|
||||
A legacy event or generation limit cannot override a later complete-state proof.
|
||||
Budget limits, lack of ready events, and unproved recurrence remain separate evidence.
|
||||
Internal diagnostic queries can cap interval-window work without reducing the recurrence proof budget.
|
||||
The standalone instruction diagnostic keeps its interval-window behavior when recurrence is not requested.
|
||||
|
||||
### Approximation and diagnostics
|
||||
|
||||
Scalar setup, copy forwarding, local reuse, and host-slice folding can change request readiness.
|
||||
These effects remain prediction limitations. Physical address reuse itself adds no execution work.
|
||||
Direct returns use the same return-operand test as lowering and preserve output multiplicity.
|
||||
Captured weights used by vector operations require host loads.
|
||||
Publication-only slices of compact results use `CopyAccessPlan` runs without an intermediate copy.
|
||||
Matrix writeback requires complete aligned array groups.
|
||||
Partial output groups, encoded layouts, unavailable geometry, and indirect output collection produce unavailable costs.
|
||||
|
||||
`--pim-periodic-diagnostics` adds resource summaries and ordered-request fingerprints.
|
||||
Normal compilation creates no fingerprints, detailed traces, or sensitivity runs.
|
||||
Optional local-copy sensitivity removes modeled copy work without changing generated code.
|
||||
It does not describe a legal transformed program or an interval bound.
|
||||
The standalone instruction diagnostic remains available for offline timing validation.
|
||||
|
||||
Checked arithmetic rejects unrepresentable sizes, loop bounds, repeated work, and service durations.
|
||||
Work-only repeats remain compact. Immutable summaries are cached within a query.
|
||||
Ordered memory and communication occurrences expand within the event budget.
|
||||
For `P` compact records, `R` expanded events, and `D` dependencies, construction costs `O(P+R+D)` time.
|
||||
With `B` processed events and `T` token propagations, queue evaluation costs `O(B log R+T)` time.
|
||||
Storage costs `O(P+R+G D)` for bounded generation count `G`, plus bounded recurrence history.
|
||||
Reports separate extraction, expansion, and queue-analysis times.
|
||||
Fingerprints compare memory and blocking-operation order, without addresses or work between requests.
|
||||
Equal fingerprints therefore do not prove equal request readiness or timing.
|
||||
|
||||
+73
-103
@@ -136,7 +136,8 @@ introduced after deferred realization, including final output collection, is
|
||||
also absent. Instruction issue, local contention, network injection queues, and
|
||||
memory arbitration remain unmodeled. Missing effects are listed in the report;
|
||||
`selection_eligible` remains false. This plan-level diagnostic does not rank
|
||||
production candidates. Production uses the instruction-level queue model below.
|
||||
production candidates. Production extracts execution events from realized Spatial
|
||||
and evaluates them with the shared queue engine.
|
||||
|
||||
For `V` events, `E` edges, and `R` recurrence edges, construction requires
|
||||
`O(T + F + S log S)` time and `O(V + E + S)` storage, for existing compute
|
||||
@@ -236,7 +237,8 @@ generations. The maximum request wait includes bootstrap. Event-index order
|
||||
resolves simultaneous readiness. A second run reverses that order and reports
|
||||
`alternative_tie_interval_ns`. These two orders are sensitivity checks, not
|
||||
bounds over every possible tie order. Clock phases and frontend overlap remain
|
||||
approximate. The standalone report remains read-only. Production selection uses the same queue model through its C++ API.
|
||||
approximate. The standalone report remains read-only.
|
||||
Production evaluates Spatial-derived events with the shared queue engine.
|
||||
|
||||
For `R` global requests, the queue mode adds `O(R)` events and dependencies.
|
||||
For `V` resulting events, `E` dependencies, and generation bound `K`, execution
|
||||
@@ -250,120 +252,88 @@ The standalone frontend retains the recurrence witness. Neither analysis changes
|
||||
|
||||
## Default throughput selection
|
||||
|
||||
Full PIM code generation performs these steps for `--pipeline > 1`.
|
||||
`--pim-only-codegen` retains the physical schedule already present in its input.
|
||||
Full PIM code generation uses Spatial-only queue-aware selection for `--pipeline > 1`.
|
||||
Latency PEFT and `--pim-only-codegen` retain their existing behavior.
|
||||
Intermediate emission retains the original schedule and stops at its requested stage.
|
||||
Its schedule can differ from the final program.
|
||||
|
||||
The normal compilation workflow is:
|
||||
The compiler performs these steps:
|
||||
|
||||
1. Run the ONNX frontend, layout planning, common lowering, and graph preparation once.
|
||||
2. Generate at most eleven verified physical schedules from the existing searches.
|
||||
3. Remove duplicate placements, including their core order and stage identities.
|
||||
4. Clone the prepared module for each candidate using MLIR's lossless `IRMapping`.
|
||||
5. Remap each schedule's compute identities to the clone.
|
||||
6. Realize communication and lower the clone through verification and instruction selection.
|
||||
7. Generate binary instruction records in memory, without weights, exports, or candidate files.
|
||||
8. Run both static controller-arbitration tie policies on that instruction program.
|
||||
9. Select an eligible candidate and emit only its normal program.
|
||||
1. Run the frontend, layout planning, and graph preparation once.
|
||||
2. Generate at most eleven legal schedules from the existing searches.
|
||||
3. Remove duplicate physical placements, including stage identities and core order.
|
||||
4. Realize each candidate in an independent clone of the prepared checkpoint.
|
||||
5. Query the target adapter over realized Spatial IR, then release the clone.
|
||||
6. Require supported static forms, available costs, and proved modeled recurrence for every candidate.
|
||||
7. Select a candidate with the existing 2.1% selection margin.
|
||||
8. Realize the selected schedule again from the unchanged checkpoint.
|
||||
9. Lower, allocate, verify, and emit only the selected program.
|
||||
|
||||
Immutable attributes, including constants and weights, remain shared in the MLIR
|
||||
context. Candidate operations, values, communication plans, and synchronization
|
||||
state remain independent. Trials never mutate the prepared checkpoint. Candidates
|
||||
run sequentially. At most one best lowered module survives between trials.
|
||||
The retained module follows the conservative selection rule throughout evaluation.
|
||||
A close alternative does not evict candidate zero. Unsupported timing contracts
|
||||
and synchronization ablation generate only the original schedule and lower it
|
||||
once. The compiler checks this before collecting alternatives. The frontend is
|
||||
not repeated.
|
||||
A single candidate skips event extraction, queue analysis, recurrence proof, and comparison.
|
||||
It is realized and lowered once, even when optional timing is unavailable.
|
||||
No rejected candidate enters PIM IR or instruction generation during cost evaluation.
|
||||
Constants and weights remain shared immutable attributes in the MLIR context.
|
||||
Candidate operations, communication plans, and synchronization state remain independent.
|
||||
No full candidate compilation directories are created.
|
||||
|
||||
Intermediate targets (`--EmitSpatial`, `--EmitPim`, and `--EmitPimBufferized`)
|
||||
retain the original schedule. They do not perform queue-aware selection or run
|
||||
transformations beyond the requested stage. Their schedule can therefore differ
|
||||
from final code generation. Full PIM code generation uses queue-aware selection.
|
||||
`SchedulingTarget::estimateRealizedScheduleCost` is the read-only whole-schedule query.
|
||||
Its typed result carries both intervals, recurrence evidence, static lowering support,
|
||||
failure reasons, and the selection margin. Unknown support remains explicit.
|
||||
The target supplies model evidence. Spatial applies the 2.1% selection policy margin.
|
||||
Selection does not read JSON diagnostics. Reports serialize the typed results.
|
||||
Spatial owns candidate generation, legality, placement, and target-neutral comparison.
|
||||
The PIM adapter owns execution-event extraction, instruction timing, and resource contention.
|
||||
The shared queue engine models controller arrival arbitration and cross-generation dependencies.
|
||||
The compiler does not execute candidate programs or invoke a simulator.
|
||||
|
||||
The PIM compiler owns instruction timing and controller behavior. Spatial owns
|
||||
legal candidate generation and schedule identity remapping. `PimPeriodicAnalysis`
|
||||
is the single instruction-level timing implementation. `raptor-periodic` is its
|
||||
read-only diagnostic frontend. The compiler invokes neither that executable nor
|
||||
an external selection script.
|
||||
Both arbitration policies must establish complete-state recurrence within bounded analysis budgets.
|
||||
Their estimates are sensitivity checks, not formal bounds.
|
||||
The candidate with the lowest larger estimate must separate from the original schedule.
|
||||
Comparison uses `[min(ties)/1.021, max(ties)/0.979]`.
|
||||
Close alternatives retain candidate zero. The 2.1% margin is a policy heuristic.
|
||||
Spatial timing predictions have no formal accuracy bound.
|
||||
The search finds the best distinguishable candidate in its bounded set, without global optimality.
|
||||
|
||||
`SchedulingTarget::prepareScheduleCost` is an optional whole-schedule cost query.
|
||||
It accepts a verified target-lowered module and returns an opaque program identity
|
||||
and a deferred static evaluation. Spatial compares the resulting interval
|
||||
estimates and applies the target's reported uncertainty. Missing uncertainty
|
||||
makes an estimate ineligible. The target owns instruction extraction,
|
||||
protocol timing, contention, and unavailable-result reasons. Preparation and
|
||||
evaluation do not change the candidate. Equal program identities avoid repeated
|
||||
queue analysis. An absent query retains the original schedule.
|
||||
If generation yields one distinct schedule, no comparison is required. The
|
||||
compiler realizes and lowers it once, without a trial clone, duplicate
|
||||
instruction generation, or queue analysis. The selection report records this
|
||||
case separately from unavailable estimates. Final code generation is unchanged.
|
||||
Unavailable timing, unknown static support, or unproved recurrence stops a multi-candidate comparison.
|
||||
The diagnostic identifies each affected candidate and property.
|
||||
The compiler does not silently exclude unknown candidates or use instruction-level fallback selection.
|
||||
|
||||
PIM transport details reside in `PimInstructionTiming`. The optional plan-level
|
||||
diagnostic also belongs to the PIM compiler. Spatial supplies its physical plans
|
||||
through an injected reporting callback; it does not encode the PIM handshake.
|
||||
The instruction emitter remains the source of register setup, address-dependent
|
||||
instruction suppression, loop expansion, and physical array-group identity.
|
||||
Candidate evaluation uses this emitter in memory after local-memory planning.
|
||||
It does not reconstruct these rules from scalar Spatial operation costs.
|
||||
Static preflight does not prove final backend legality.
|
||||
The selected candidate runs through normal bufferization, allocation, and backend verification.
|
||||
A backend owner can mark a resource-limit diagnostic as candidate-specific.
|
||||
Currently, the local-memory allocator marks signed 32-bit address-space exhaustion.
|
||||
The compiler discards that failed clone, explicitly records its rejection, and selects again from the remaining estimated schedules.
|
||||
The first remaining schedule becomes the reference for the same selection policy.
|
||||
Each schedule is attempted at most once. No graph or placement constraints are relaxed.
|
||||
Unclassified or systemic backend failures stop compilation immediately.
|
||||
Code-generation failures also stop compilation when recovery cannot be justified.
|
||||
If every candidate fails, one diagnostic lists all attempted candidates and causes.
|
||||
|
||||
Production projects native fp32 transfer sizes and vector widths to the existing
|
||||
oracle int8 timing contract. It preserves instruction counts, matrix precision,
|
||||
vector element counts, synchronization, and transfer identities. This projection
|
||||
does not change the emitted native program. Unsupported widths, targets without
|
||||
complete timing, and unsupported instruction semantics produce explicit fallback
|
||||
reasons. Synchronization ablation retains the original schedule.
|
||||
|
||||
Both arbitration tie runs must converge within the existing generation and event
|
||||
budgets. Their estimates are sensitivity checks, not formal bounds. Duplicate
|
||||
instruction programs are analyzed once. The candidate with the lowest larger
|
||||
estimate must separate from the original schedule. Close alternatives do not
|
||||
cancel a gain that separates from the original. Comparison uses `[min(ties)/1.021, max(ties)/0.979]`. The fixed 2.1% prediction uncertainty
|
||||
covers offline validation error with upward rounding. It is a selection margin,
|
||||
not a fitted instruction latency or a guaranteed error bound. Overlapping ranges
|
||||
with the original retain candidate zero. Missing original estimates also retain candidate zero.
|
||||
Unavailable alternatives cannot displace an eligible original. This search finds
|
||||
the best distinguishable candidate in its bounded set; it does not establish
|
||||
global optimality.
|
||||
|
||||
`reports/pipeline_selection.json` records candidate identities, estimates,
|
||||
selection reasons, and generation, lowering, instruction-generation, queue-analysis,
|
||||
and finalization times. The selected verified lowered module and its captured
|
||||
schedule report are reused without repeating materialization or communication
|
||||
realization. Memory reports come from normal final code generation.
|
||||
With `--enable-timing`, candidate summaries also contain per-pass lowering times
|
||||
and operation/value counts before bufferization and instruction generation.
|
||||
Instruction-generation summaries separate preparation from per-core emission.
|
||||
Explicit Spatial exports, IR snapshots,
|
||||
and plan-level periodic diagnostics reconstruct the selected Spatial schedule
|
||||
because those outputs require pre-lowering operations. This optional work does
|
||||
not change the retained instruction program. Candidate instructions and rejected
|
||||
IR are released immediately. No temporary compilation directories are created.
|
||||
`--pim-dump-ir` explicitly enables diagnostic IR snapshots;
|
||||
these snapshots elide large constants and cannot serve as lossless checkpoints.
|
||||
`reports/pipeline_selection.json` records Spatial costs, eligibility, selection, and backend attempts.
|
||||
It also records candidate generation, realization, extraction, expansion, queue, lowering, and finalization times.
|
||||
`--enable-timing` adds per-pass lowering times and IR operation/value counts.
|
||||
Final instruction generation uses the normal compiler timing report.
|
||||
Explicit Spatial exports and IR dumps reconstruct pre-lowering artifacts for the selected schedule.
|
||||
They do not change the emitted program. Diagnostic MLIR dumps elide large constants and are not lossless checkpoints.
|
||||
|
||||
### Static analysis, diagnostics, and external validation
|
||||
|
||||
Production decisions use only the input program, compiler options, candidate
|
||||
instructions and plans, and configured target resources and timing. The static
|
||||
model executes deterministic abstract events. It does not execute the generated
|
||||
program. It reads no benchmark CSV, profiling trace, measured latency cache, or
|
||||
reference artifact. Identical static inputs produce the same decision regardless
|
||||
of historical measurements. Throughput deferred-demand ordering uses IR order,
|
||||
rather than allocation addresses. Latency PEFT and its demand ordering are unchanged.
|
||||
Production decisions use the input graph, compiler options, physical plans, and configured target parameters only.
|
||||
Identical static inputs produce the same decision regardless of historical measurements.
|
||||
There are no measured-latency caches, workload lookup tables, or fitted timing corrections.
|
||||
|
||||
Optional diagnostics expose recurrence witnesses, instruction timing, and resource
|
||||
service. Offline Pimsim fast-mode measurements validate these predictions and
|
||||
candidate rankings. Simulator results never enter production selection. Timing
|
||||
corrections must follow verified hardware behavior or configured parameters.
|
||||
`raptor-periodic` retains the instruction-derived analyzer as a standalone validation frontend.
|
||||
It shares the same timing definitions and queue engine with Spatial event evaluation.
|
||||
Optional diagnostics expose resource work, recurrence, and ordered-request fingerprints.
|
||||
Offline Pimsim fast-mode runs validate predictions and emitted programs.
|
||||
Simulator measurements never enter production selection.
|
||||
|
||||
For `B <= 11` schedules, `T` compute instances, and `P` cores, captured schedules
|
||||
use `O(B(T+P))` storage. Placement deduplication takes `O(B²T)` time. Each distinct
|
||||
finalist requires downstream lowering and one instruction scan. Queue execution
|
||||
uses the bounded complexity stated above. Peak storage includes the prepared
|
||||
module, one best lowered module, one trial, and one queue graph. It does not scale
|
||||
with retained complete candidate programs. Maximum-cycle-ratio diagnostics do not
|
||||
run in the candidate evaluation loop.
|
||||
For `C <= 11` candidates, scheduling metadata uses `O(C(T+P))` storage for `T` compute instances and `P` cores.
|
||||
Placement deduplication costs `O(C²T)` time.
|
||||
Candidate realization and extraction are sequential; complete candidate modules are not retained.
|
||||
Normal successful compilation performs one candidate-specific backend lowering.
|
||||
Recovery performs at most `C` lowerings. Retry selection costs `O(C²)` time and `O(C)` metadata.
|
||||
The bounded queue-analysis costs are described in the implementation notes.
|
||||
|
||||
## Capacity and recovery
|
||||
|
||||
|
||||
Reference in New Issue